x*******r 发帖数: 276 | 1 拿到pre drywall inspection report,好多问题,把report发给builder了,怎么知道
他们把该补的补了,该修的修好呢。builder说按照schedule,明天该上insulation,
但是我担心report上的问题都还没解决。应该怎么跟builder谈判,督促他们。 |
x****u 发帖数: 12955 | 2
Did it pass inspection? If not, then they are required to fix everything
wrong and ask for re inspection before proceeding to next stage.
If it did pass inspection, but has some issues that you don't like to live
with, then you will have to request builder to fix them, even if it means
delays. And you will have to personally check the work against what the
report says to make sure they did it.
【在 x*******r 的大作中提到】 : 拿到pre drywall inspection report,好多问题,把report发给builder了,怎么知道 : 他们把该补的补了,该修的修好呢。builder说按照schedule,明天该上insulation, : 但是我担心report上的问题都还没解决。应该怎么跟builder谈判,督促他们。
|
x*******r 发帖数: 276 | 3 Thank you very much for your suggestions.
【在 x****u 的大作中提到】 : : Did it pass inspection? If not, then they are required to fix everything : wrong and ask for re inspection before proceeding to next stage. : If it did pass inspection, but has some issues that you don't like to live : with, then you will have to request builder to fix them, even if it means : delays. And you will have to personally check the work against what the : report says to make sure they did it.
|
L*1 发帖数: 11537 | 4 有小问题没关系,只要pass inspection。有些你认为的问题其实不是问题。
最重要的是把管道,布线什么的都照下来存档。 |
x*******r 发帖数: 276 | 5 怎么看出来passinspectio?报告上没说阿
【在 L*1 的大作中提到】 : 有小问题没关系,只要pass inspection。有些你认为的问题其实不是问题。 : 最重要的是把管道,布线什么的都照下来存档。
|
L*1 发帖数: 11537 | 6 我们这里inspection是政府做的,没有OK的话,builder不能继续下一步的。 |