由买买提看人间百态

boards

本页内容为未名空间相应帖子的节选和存档,一周内的贴子最多显示50字,超过一周显示500字 访问原贴
Law版 - 大侠们看过来, LR
相关主题
你们谁能帮我这篇文章submit到harvard law review要申请JD、读JD的还有JD毕业的
求助:市府不按时赔偿,怎么办?歧视疑问
New York Changes LL.M. Requirements for Foreign Lawyers to Sit State BarAgent 诈骗!
和解协议Stipulation of settlement能有多大效用???help me with a question from Oct. 99
Business Law Notes-1请问各位,我这种情况去和landlord argue,能成功么?
Negative Declaration中国的法律
Honda Warranty的问题租的房子有bed bugs,能中止合同吗?
请大家帮忙找一篇文章 (转载)Severance package (转载)
相关话题的讨论汇总
话题: costs话题: cost话题: contractor话题: stipulates话题: kind
进入Law版参与讨论
1 (共1页)
s*******1
发帖数: 135
1
Construction contractors working on the cutting edge of technology nearly
always work on a "cost plus" basis only. One kind of cost-plus contract
stipulates the contractor's profit as a fixed percentage of the contractor's
costs; the other kind stipulates a fixed amount of profit over and above
costs. Under the first kind of contract, higher costs ield higher profits
for the contractor, so this is where one might expect final costs in excess
of original cost estimates to be more common. Paradoxi
x**y
发帖数: 10012
2
c肯定不对
de里面选一个的话
我看选d吧 因为要解释的是为什么 A B 都超预算 但是B反而比A超的更离谱
d给了解释 说A可以查帐 B不查帐所以浪费多
e没看出来说啥 就算profit modest了 我也没看出直接原因导致B比A更容易超阿

's
excess

【在 s*******1 的大作中提到】
: Construction contractors working on the cutting edge of technology nearly
: always work on a "cost plus" basis only. One kind of cost-plus contract
: stipulates the contractor's profit as a fixed percentage of the contractor's
: costs; the other kind stipulates a fixed amount of profit over and above
: costs. Under the first kind of contract, higher costs ield higher profits
: for the contractor, so this is where one might expect final costs in excess
: of original cost estimates to be more common. Paradoxi

z***e
发帖数: 1757
3
D.
D**********s
发帖数: 320
4
D.
Cost overrun means the actual cost exceeds the estimate. If the client is
more likely to scrutinize the fixed percentage contract, the costs are more
likely to be controlled.
E is wrong because inflated estimated costs actually make cost-overrun
harder so it undermines the conclusion.
d*****i
发帖数: 43
5
不是大侠,D。
r********l
发帖数: 24
6
D.
C introduces new information - sizable; in addition, it does not explain why
the first one is more common.
For E, I think it is reverse.

's
excess

【在 s*******1 的大作中提到】
: Construction contractors working on the cutting edge of technology nearly
: always work on a "cost plus" basis only. One kind of cost-plus contract
: stipulates the contractor's profit as a fixed percentage of the contractor's
: costs; the other kind stipulates a fixed amount of profit over and above
: costs. Under the first kind of contract, higher costs ield higher profits
: for the contractor, so this is where one might expect final costs in excess
: of original cost estimates to be more common. Paradoxi

s*******1
发帖数: 135
7
你们都这么厉害,不知道我是作题不够多还是思路有问题。C 的最后部分but they
do so only when the contractor's profit varies with cost 干扰我,不敢选。
1 (共1页)
进入Law版参与讨论
相关主题
Severance package (转载)Business Law Notes-1
LD在maternity leave被裁,求帮助 (转载)Negative Declaration
求助:如何到small claim court告contractorHonda Warranty的问题
转让LSAT材料请大家帮忙找一篇文章 (转载)
你们谁能帮我这篇文章submit到harvard law review要申请JD、读JD的还有JD毕业的
求助:市府不按时赔偿,怎么办?歧视疑问
New York Changes LL.M. Requirements for Foreign Lawyers to Sit State BarAgent 诈骗!
和解协议Stipulation of settlement能有多大效用???help me with a question from Oct. 99
相关话题的讨论汇总
话题: costs话题: cost话题: contractor话题: stipulates话题: kind