s*******1 发帖数: 135 | 1 Construction contractors working on the cutting edge of technology nearly
always work on a "cost plus" basis only. One kind of cost-plus contract
stipulates the contractor's profit as a fixed percentage of the contractor's
costs; the other kind stipulates a fixed amount of profit over and above
costs. Under the first kind of contract, higher costs ield higher profits
for the contractor, so this is where one might expect final costs in excess
of original cost estimates to be more common. Paradoxi |
x**y 发帖数: 10012 | 2 c肯定不对
de里面选一个的话
我看选d吧 因为要解释的是为什么 A B 都超预算 但是B反而比A超的更离谱
d给了解释 说A可以查帐 B不查帐所以浪费多
e没看出来说啥 就算profit modest了 我也没看出直接原因导致B比A更容易超阿
's
excess
【在 s*******1 的大作中提到】 : Construction contractors working on the cutting edge of technology nearly : always work on a "cost plus" basis only. One kind of cost-plus contract : stipulates the contractor's profit as a fixed percentage of the contractor's : costs; the other kind stipulates a fixed amount of profit over and above : costs. Under the first kind of contract, higher costs ield higher profits : for the contractor, so this is where one might expect final costs in excess : of original cost estimates to be more common. Paradoxi
|
z***e 发帖数: 1757 | |
D**********s 发帖数: 320 | 4 D.
Cost overrun means the actual cost exceeds the estimate. If the client is
more likely to scrutinize the fixed percentage contract, the costs are more
likely to be controlled.
E is wrong because inflated estimated costs actually make cost-overrun
harder so it undermines the conclusion. |
d*****i 发帖数: 43 | |
r********l 发帖数: 24 | 6 D.
C introduces new information - sizable; in addition, it does not explain why
the first one is more common.
For E, I think it is reverse.
's
excess
【在 s*******1 的大作中提到】 : Construction contractors working on the cutting edge of technology nearly : always work on a "cost plus" basis only. One kind of cost-plus contract : stipulates the contractor's profit as a fixed percentage of the contractor's : costs; the other kind stipulates a fixed amount of profit over and above : costs. Under the first kind of contract, higher costs ield higher profits : for the contractor, so this is where one might expect final costs in excess : of original cost estimates to be more common. Paradoxi
|
s*******1 发帖数: 135 | 7 你们都这么厉害,不知道我是作题不够多还是思路有问题。C 的最后部分but they
do so only when the contractor's profit varies with cost 干扰我,不敢选。 |