Eric Johnson makes billiard balls in his New England Plant. With recent
increases in his costs, he has a new- found interest in efficiency. Eric is
interested in determining the productivity of his organization. He would
like to know if his organization is maintaining the manufacturing average of
3% increase in productivity. He has the following data representing a
m | b*****n 发帖数: 4122 | 2 Task time estimates for a production line setup project at Robert Klassen’s
Ontario factory are as
follows.
(a) Draw the project network.
(b) Identify the critical path.
(c) What is the expected project length?
(d) Draw a Gantt chart for the project. | x****l 发帖数: 7895 | |
|